Secured Network Solutions Past Performance
Joint Forces Command Center
- Fiber to the Desktop-18K+ LC Keyed Connectors for 6 Fiber Networks
- Classified and Unclassified-Physical Separation Requirements for Copper
- PDS Pathways-Installation in occupied areas
- Server Room Buildout -80 Floor Mounted Full Size Cabinets
- Flexible Network Distribution Boxes-20’ whips allowing WAO to be Relocated as Needed
- Flexible Building Layout-False Floor Access
- Large Cable Infrastructure-500K of Cat6 Cable/450K of MM
17,000’ OSP Duct Bank Infrastructure
- High Pair Count Cables-1800Pr Copper & 288-Strand SM Fiber
- Copper Splicing in Every Manhole-Re-entrable Splice Cases for Future Growth
- Building Surge Protection-Pairs Terminated on Gas Modules
- Future Ready Pathways-3-Cell Maxcell Innerduct
- Confined Space Entry-Tools & Certs-Tripods, Blowers, Sampler
- Continuous Fiber (No Splices)-Limited Only by Reel Lengths
- Service Loops-100’ Fiber Service Loops in Each Manhole
|